Located in Akwa Ibom State, Nigeria, this project is invested by PADAH LNG FZE. The Group Company, as a specialized subcontractor, was responsible for the full-site piling and ground improvement works.
The project commenced on March 21, 2024, and was completed on June 25, 2025, a total of 462 days. The scope included the installation of 12,244 cement mixing piles, each with a diameter of 0.5 meters and a length of 7 meters, along with 776 bored piles with a diameter of 1.4 meters and lengths of 56.7 meters and 57 meters.
Throughout the construction process, the project team consistently prioritized the principle of "Safety First," ensuring a healthy, safe, and environmentally compliant worksite for all personnel. The project successfully achieved its "zero-accident target," with no occurrences of occupational diseases, infectious disease incidents, or environmental pollution events, thereby guaranteeing safe and civilized construction.
All contractual requirements were fully met, and the project quality and management standards were highly recognized by both the client and the main contractor, laying a solid foundation for future cooperation.